Illustrative technician monitoring controllable data-centre commissioning load equipment

Commissioning use | Functional performance

Functional Performance Testing Equipment & Support

Prove system performance under controlled load.

Functional performance testing verifies how individual systems and subsystems respond under intended operating conditions and planned failure scenarios. Controllable load equipment creates repeatable demand without relying on production compute.

Illustrative AI-generated image

Individual systems need to perform under realistic, repeatable demand.

Many mission-critical projects refer to this stage as Level 4 or Functional Performance Testing. Exact terminology, responsibilities and procedures are defined by the project commissioning plan.

Controlled electrical and thermal load equipment can support testing of:

UPS systemsGeneratorsATS / STSElectrical distributionRack PDUs / buswayCooling systemsCDUs and pumpsControls and alarmsRedundancy sequences

Low-load operation may not reveal design-load behaviour.

Systems may respond differently as power demand, thermal output, flow or control interaction approaches intended operating conditions. Controlled load lets the project team progressively exercise infrastructure at defined operating points while production compute remains outside the test.

Load levels, duration, sequences and pass/fail thresholds are project-specific. AMOR configures and operates the equipment against the approved procedure rather than imposing universal criteria.

Turn an approved test step into controlled infrastructure demand.

The CxA directs the test. AMOR supports the temporary load condition and equipment response required to execute it.

01

Define the condition

The owner, CxA and engineering team establish the operating condition, scenario and acceptance requirements.

02

Configure the load

AMOR aligns equipment capacity, electrical and liquid interfaces, control grouping and deployment with the approved procedure.

03

Apply controlled demand

Loads are introduced and changed at the approved operating points while the project team witnesses system response.

04

Maintain repeatability

Predictable load conditions allow testing, issue resolution and repeat runs without production servers.

05

Support closeout

AMOR supports equipment operation, troubleshooting and equipment-side data capture where applicable.

Exercise power, cooling and control subsystems.

Test scenarios remain defined and witnessed under the project commissioning plan.

Critical power

UPS loading, generator response, transfer devices, distribution paths and redundancy.

Rack distribution

Busway, rack PDU and branch-path behaviour under controlled rack demand.

Cooling response

CDUs, pumps and controls responding to rack or zone thermal load.

Controls & alarms

BMS, EPMS and equipment alarms observed as approved operating conditions change.

Equipment + field support + project response.

AMOR combines specialized temporary load equipment with the coordination, electrical capability and technical response required to deploy it around real construction schedules.

Equipment availability and deployment capacity are confirmed against each project's schedule and requirements.

  • Specialized high-density equipment
  • Rack-scale through MW-scale load
  • Air, liquid and hybrid simulation
  • North American project coordination
  • Electrical field capability
  • Project-specific technical configuration

Technical discovery

Discuss your FPT requirements

Share what is currently known. These details guide the first technical review and do not all need to be complete before a discussion.

01Project location02Commissioning stage03Planned test date04Electrical load requirement05Rack density and voltage06Air / liquid / hybrid cooling07Anticipated equipment quantity08Test duration09Owner / CxA requirements, if available