240 kW Hybrid Air + Liquid AI Rack Emulator
Hybrid rack-scale electrical and thermal load simulation for high-density AI commissioning.

AMOR GROUP | MISSION CRITICAL
Explore AMOR equipment datasheets, commissioning resources and technical guidance for high-density AI data centres, liquid-cooling infrastructure and mission-critical electrical systems.
Browse equipment datasheetsFeatured technical documents
Four approved AMOR product resources covering rack, cooling-zone and facility-level commissioning load.
DS-01Equipment datasheet
Hybrid rack-scale electrical and thermal load simulation for high-density AI commissioning.
DS-02Equipment datasheet
Rack-scale liquid thermal emulation for high-density liquid-cooled AI infrastructure.
DS-03Equipment datasheet
Scalable liquid load platforms for CDU testing, thermal commissioning and AI hall validation.
DS-04Equipment datasheet
High-capacity electrical load systems for generators, UPS systems, distribution infrastructure and IST.
Browse by technical area
Move from the rack, through the cooling system, to the wider facility power and integrated test condition.
Commissioning Resources
Technical guidance for common mission-critical commissioning stages, with owner and CxA responsibilities kept clear.
Commissioning use | Functional performance
Functional performance testing verifies how individual systems and subsystems respond under intended operating conditions and planned failure scenarios. Controllable load equipment creates repeatable demand without relying on production compute.
Explore FPT support CR-02Commissioning use | Liquid cooling
Controlled rack and hall-scale thermal loads allow the project team to observe the liquid-cooling system at realistic demand before production servers are installed or placed at risk.
Explore heat load testing CR-03Commissioning use | Integrated systems
Integrated Systems Testing examines how power, cooling, controls and backup systems respond together. AMOR provides predictable electrical and thermal test conditions under the owner/CxA-approved commissioning plan.
Explore IST supportTechnical Insights
Three published perspectives for owners, CxAs, engineers and project teams working through liquid cooling, temporary load and next-generation power architecture.
Illustrative AI-generated image
Manufacturing partner reference · Asia
Illustrative AI-generated imageBuilt to expand
The library is structured to grow with AMOR's equipment platform, commissioning experience and next-generation infrastructure work.
Project-specific equipment review
Every commissioning program is different. Send AMOR your project requirements and we can help identify an appropriate equipment configuration for the planned electrical and thermal test conditions.