Test the infrastructure before the compute goes live.

AMOR provides controllable electrical and thermal load equipment together with deployment and field support for functional testing, heat-load testing and integrated systems testing of mission-critical infrastructure.

Critical infrastructure must be proven before production compute is available.

Modern AI data centres can impose very high electrical and thermal rack densities. The project team still needs to demonstrate capacity, sequence response and recovery without exposing expensive production servers to commissioning risk.

Temporary controllable loads allow the approved test plan to demonstrate that:

  • Electrical distribution carries intended load
  • UPS and generators perform correctly
  • Transfer and redundancy sequences operate as intended
  • Cooling systems reject the design heat load
  • CDUs and liquid distribution respond correctly
  • Controls and alarms respond correctly
  • Infrastructure recovers after simulated failures

Apply controlled demand where the infrastructure needs to be proven.

Different equipment families reproduce electrical and thermal demand at facility, distribution, rack and cooling-system levels.

Rack, hall and facility-level test capacity.

Each layer can be deployed independently or coordinated as part of a wider test program.

01 | Rack level

AI rack emulation

Hybrid Air + Liquid and Full-Liquid AI Rack Emulators

  • Rack electrical loading
  • High-density thermal simulation
  • CDU branch validation
  • Rack cooling response
  • Power-path testing
  • Failure and recovery scenarios
View AI rack emulators
02 | Cooling / hall level

Thermal capacity at scale

300-600 kW High-Capacity Liquid Load Banks

  • Cooling-zone load simulation
  • CDU capacity testing
  • Liquid distribution validation
  • Thermal stabilization
  • Redundancy testing
  • Expansion and retrofit validation
View liquid load banks
03 | Facility power level

Electrical infrastructure

MW-Scale LV/MV Commissioning Load Banks

  • Generator testing
  • UPS validation
  • Switchgear and feeder testing
  • Transformer loading
  • Emergency-power sequences
  • Integrated-system load scenarios
View MW-scale load banks

Controlled load becomes critical when systems must perform.

Commissioning terminology and stage definitions vary by owner and CxA. The following represents a common mission-critical commissioning progression.

01Factory / pre-delivery
02Installation & QA/QC
03Start-up
04Functional performance testingAMOR equipment focus
05Heat load testingAMOR equipment focus
06Integrated systems testingAMOR equipment focus
07Handover / operations

Equipment is only part of the test.

Large-scale temporary loads must be selected, transported, staged, connected, configured, operated, monitored, repositioned and supported as site conditions and testing progress.

RequirementsConfigureMobilizeConnectTestSupportDemobilize
01

Project requirement review

Review rack density, power and cooling architecture, test capacity and commissioning schedule.

02

Equipment configuration

Select the rack emulators, liquid loads and MW-scale electrical load banks appropriate to the approved procedures.

03

Mobilization

Coordinate transportation, staging, equipment movement and site logistics.

04

Site readiness

Coordinate temporary electrical connections, hoses, manifolds, CDU interfaces and placement with project trades.

05

Setup

Connect and configure equipment for the approved commissioning procedure.

06

Operation support

Support staged load changes, monitoring and equipment operation during testing.

07

Troubleshooting & data

Adjust equipment-side interfaces and assist with equipment data capture where applicable.

08

Demobilization

Safely disconnect and remove temporary commissioning equipment after testing is complete.

Equipment + field support + project response.

AMOR combines specialized temporary load equipment with the coordination, electrical capability and technical response required to deploy it around real construction schedules.

Equipment availability and deployment capacity are confirmed against each project's schedule and requirements.

  • Specialized high-density equipment
  • Rack-scale through MW-scale load
  • Air, liquid and hybrid simulation
  • North American project coordination
  • Electrical field capability
  • Project-specific technical configuration

Technical discovery

Request a project review

Share what is currently known. These details guide the first technical review and do not all need to be complete before a discussion.

01Project location02Commissioning stage03Planned test date04Electrical load requirement05Rack density and voltage06Air / liquid / hybrid cooling07Anticipated equipment quantity08Test duration09Owner / CxA requirements, if available